(a)All plans and specifications for the construction or renovation of Office of Children and Family Services (OCFS) secure facilities shall be submitted to the State Commission of Correction (the commission) for review and approval.
(b)Such approval by the commission shall be obtained before a construction or renovation project is advertised for bids. If a bidding procedure will not be followed, commission approval must be obtained before any construction or renovation begins.