(a)The director shall apply to the commission for a revision of the certified maximum facility capacity of a facility upon a change in any of the factors delineated in section 7320.5(b) of this Part.
(b)Such application shall be made in writing and include the specific facts, reasons and special circumstances underlying the request.
(c)Within 60 days after receipt, the commission shall review such application and, following consultation with OCFS, forward its determination in writing to the director.