New York regulations

9 NYCRR 575.2

Executive Department

Browse New York regulations by title, part, and section.

Measuring distances

Measuring distances

Compiled text through Sep 15, 2021

Register checked through Jul 29, 2026

No later Register activity identified in this check.

Dates and status
Compiling agency
Executive Department
Text status
Source receipt
Compiled text through
Sep 15, 2021
Register checked through
July 29, 2026/Vol. XLVIII, Issue 30 (2026-07-29)
Activity status
No later Register activity identified in this check.
Source snapshot
Jun 6, 2026
(a)All distances specified in the shoreline restrictions are measured horizontally. Shoreline lot widths are measured along the shoreline as it winds and turns at the mean high water mark.
(b)Building setback restrictions are measured along the shortest line between any point of the structure and any point on the mean high water mark.
(c)Wastewater treatment system setbacks are measured along the shortest line between any point of the seepage pit, drainage field or other leaching facility and any point on the mean high water mark.
(d)In the case of the Great Sacandaga Lake, mean high water mark shall mean the spillway elevation contour of 771 feet above mean sea level.