General project requirements
Compiled text through Sep 15, 2021
Register checked through Jul 29, 2026
No later Register activity identified in this check.
Dates and status
- Compiling agency
- Executive Department
- Text status
- Source receipt
- Compiled text through
- Sep 15, 2021
- Register checked through
- July 29, 2026/Vol. XLVIII, Issue 30 (2026-07-29)
- Activity status
- No later Register activity identified in this check.
- Source snapshot
- Jun 6, 2026
In order to be eligible for State assistance under this Part, the entire project must be:
(a)recommended to the commissioner by the governing body of the project sponsor or where the project sponsor is a State agency, its chief executive; and
(b)located within the physical boundaries of the State of New York.