(a)If an application is not complete, the office will contact the applicant for additional information within 15 calendar days of its receipt.
(b)Except as provided in subdivision (c) of this section, if the application is complete, the office will either issue or deny the permit within 15 calendar days of its receipt.
(c)If the office needs additional time to review a permit application, it will notify the applicant within 15 calendar days that additional review time is required and indicate when it will act upon the permit request.
(d)If the office denies an application for a permit, it will notify the applicant of its reasons why the permit was not issued. Any application and/or permit fees will be returned to the applicant.
(e)This section does not apply to camping and cabin permits which are issued through the office's camping reservation system.