Final decision
Compiled source label: current through Jun 30, 2022
Register checked through July 8, 2026/Vol. XLVIII, Issue 27 (2026-07-08) - no later Register activity found for this section
What LawEngine checked
- Status
- Source receipt
- Compiled source current through
- Jun 30, 2022
- Register checked through
- July 8, 2026/Vol. XLVIII, Issue 27 (2026-07-08)
- Register activity status
- no later Register activity found
- LawEngine source snapshot
- Jun 6, 2026
A stipulation executed by all parties resolving any or all issues removes such issue(s) from further consideration in the proceeding. Within five days of the execution of a stipulation, the applicant shall serve a copy of the fully executed stipulation on all parties and file a copy of the fully executed stipulation with the ALJ. Upon receipt of an executed stipulation that resolves all issues in the proceeding, the ALJ shall close the proceeding and remand the matter to office staff to continue processing the application to issue the requested siting permit.
The final decision of the executive director shall be issued within 30 days after receipt of all comments on the recommended decision and hearing report.
At any time prior to issuing the final decision, the executive director or the ALJ may direct that the hearing record be reopened to consider significant new evidence.