Publication of draft siting permit
Compiled source label: current through Jun 30, 2022
Register checked through July 8, 2026/Vol. XLVIII, Issue 27 (2026-07-08) - no later Register activity found for this section
What LawEngine checked
- Status
- Source receipt
- Compiled source current through
- Jun 30, 2022
- Register checked through
- July 8, 2026/Vol. XLVIII, Issue 27 (2026-07-08)
- Register activity status
- no later Register activity found
- LawEngine source snapshot
- Jun 6, 2026
(a)No later than 60 days following the date upon which an application has been deemed complete, and following consultation with any relevant State agency or authority, the ORES shall publish on its website for public comment draft permit conditions prepared by the office or a statement of intent to deny.
(b)No later than 60 days following the date upon which an application has been deemed complete, a combined notice of availability of draft permit conditions or statement of intent to deny, public comment period and public comment hearing, and issues determination, as defined in section 900-8.2(d) of this Subpart, shall be published on the ORES website.