Publication of draft siting permit

You’re browsing Title 19— the Department of State’s own regulations — free.

Create a free account (no card) to open all 23 titles →

Publication of draft siting permit

Compiled source label: current through Jun 30, 2022

Register checked through July 8, 2026/Vol. XLVIII, Issue 27 (2026-07-08) - no later Register activity found for this section

What LawEngine checked
Status
Source receipt
Compiled source current through
Jun 30, 2022
Register checked through
July 8, 2026/Vol. XLVIII, Issue 27 (2026-07-08)
Register activity status
no later Register activity found
LawEngine source snapshot
Jun 6, 2026
(a)No later than 60 days following the date upon which an application has been deemed complete, and following consultation with any relevant State agency or authority, the ORES shall publish on its website for public comment draft permit conditions prepared by the office or a statement of intent to deny.
(b)No later than 60 days following the date upon which an application has been deemed complete, a combined notice of availability of draft permit conditions or statement of intent to deny, public comment period and public comment hearing, and issues determination, as defined in section 900-8.2(d) of this Subpart, shall be published on the ORES website.