Transfer applications for pending article 10 facilities

Source version current through Jul 15, 2022

Source details
NYCRR title agency
Department of State
Section status
Section source receipt
Source version current through
Jul 15, 2022
Text saved
Sep 13, 2026
Publisher current-through date
Jul 15, 2022
Source captured
Sep 13, 2026
Stored text comparison
Matches the captured source text
Related Register notice
DOS-37-20-00015-A · Adopted rule
Related notice published
Mar 3, 2021
Related notice effective date
Mar 3, 2021

New York State Register DOS-37-20-00015-A

(a)For pending article 10 facilities for which a completeness determination has been issued pursuant to PSL article 10:
(1)The applicant shall provide the following:
(i)written notice to ORES at least 14 days in advance of filing;
(ii)a copy of the written notice to the secretary of the PSC advising of the applicant’s election to be subject to Executive Law section 94-c;
(iii)a completed transfer of application form;
(iv)a copy of the application materials submitted pursuant to the PSL article 10; and, to the extent the applicant wishes to be subject to a uniform standard or condition set forth in Subpart 900-6 of this Part, an explanation as to how the PSL article 10 application materials demonstrate compliance with such permit condition;
(v)copies of documentation identifying those matters and issues that have been identified and resolved in the PSL article 10 proceeding;
(vi)any additional information that may be required in order to enable the office to make the findings and determinations required by law;
(vii)the fee to be deposited in the local agency account in an amount equal to $1,000 for each 1,000 kilowatts of capacity, which may be adjusted from time to time by the office to account for inflation; and
(viii)the ORES fee to recover the costs of reviewing and processing an application in an amount equal to $1,000 for each 1,000 kilowatts of capacity.
(2)Such applications shall be deemed complete upon filing; provided, however, that if the office determines that the applicant has not demonstrated compliance with the uniform standards and conditions set forth in Subpart 900-6 of this Part, the office will develop the necessary site-specific conditions to avoid, minimize and mitigate significant adverse environmental impacts to the maximum extent practicable, including requirements for additional compliance filings beyond those set forth in Subpart 900-10 of this Part, as necessary.
(b)Applicants for pending article 10 facilities for which the application has been filed, but has not yet been deemed to be in compliance with article 10 application requirements, shall provide the following:
(1)written notice to ORES at least 14 days in advance of filing;
(2)a copy of the written notice to the secretary of the PSC of applicant’s intent to become subject to this Part;
(3)a completed transfer of application form;
(4)the exhibits required in Subpart 900-2 of this Part;
(5)copies of documentation identifying those matters and issues that have been identified and resolved in the PSL article 10 process;
(6)any additional information that may be required in order to enable the office to make the findings and determinations required by law;
(7)the fee to be deposited in the local agency account in an amount equal to $1,000 for each 1,000 kilowatts of capacity, which may be adjusted from time to time by the office to account for inflation; and
(8)the ORES fee to recover the costs of reviewing and processing an application in an amount equal to $1,000 for each 1,000 kilowatts of capacity.
(c)For any matters and issues that have been identified and resolved in the PSL article 10 process, the siting permit will reflect such resolution and those provisions will not be the subject of any adjudicatory hearing conducted pursuant to Subpart 900-8 of this Part.
(d)The applicant shall comply with requirements for filing, service and publication of the application pursuant to section 900-1.6 of this Part.