Financing projects
Compiled source label: current through Jun 30, 2022
Register checked through July 8, 2026/Vol. XLVIII, Issue 27 (2026-07-08) - no later Register activity found for this section
What LawEngine checked
- Status
- Source receipt
- Compiled source current through
- Jun 30, 2022
- Register checked through
- July 8, 2026/Vol. XLVIII, Issue 27 (2026-07-08)
- Register activity status
- no later Register activity found
- LawEngine source snapshot
- Jun 6, 2026
(a)The commissioner may make or contract to make a State grant to a county within the budgetary appropriation therefor for payment to the county to reimburse up to a limit of 40 percent of the authorized charter expenditures or $25,000, whichever is less.
(b)Such records as shall be prescribed by the commissioner shall be maintained by the consultant and the county contracting for the project which records shall be kept on file for a period of three years after the completion of the project.